Birchwood and Spring Creek July 2020 Update

10:22AM July 08, 2020

Birchwood

The Georgetown Service Zone (phase 1) is complete.  Crews have moved on to the Parker Loop Service Zone.  Work on Parker Loop is currently about 10% complete.  We hope to have Parker Loop completed by the end of 2020.


Spring Creek

The Spring Creek and Clear Water Service Zones (phase 1) are complete.  Crews have moved on to the Idle Wild Service Zone.  We hope to have Idle Wild completed by the end of 2020.


Active Service Zones

The following hyperlink connects to a Google Map of the active service zones.  If you live within one of the red, blue, or green zones, the Twin Lakes broadband service is currently available to you.  You will need to copy and paste the hyperlink in your web browser search bar to view the map.